Date post: | 11-Mar-2023 |
Category: |
Documents |
Upload: | khangminh22 |
View: | 0 times |
Download: | 0 times |
1
Traditional Costing Systems
In Traditional Costing Systems
• Allocate overhead using a single predetermined rate.
• Job order costing: direct labor cost is assumed to be the
relevant activity base.
• The assumption was satisfactory when direct labor was a
major portion of total manufacturing costs.
• Wide acceptance of a high correlation between direct labor
and overhead costs.
• In traditional cost accounting, only manufacturing cost are
assigned to products
• Administrative expenses are treated as period expenses
and are not assigned to products.
2
The Need for a New Approach
Tremendous change in manufacturing and service
industries.
Decrease in the amount of direct labor used.
Significant increase in total overhead costs.
Inappropriate to use plant-wide predetermined overhead
rates when a lack of correlation exists.
Complex manufacturing processes may require multiple
allocation bases; this approach is called Activity-Based
Costing (ABC).
3
Activity-Based Costing System
In activity-based costing (ABC), products are assigned all
of the overhead cost.
Activity-based costing (ABC) refines a costing system by
identifying individual activities as the fundamental cost
objects.
An activity is an event, task, or unit of work with a
specified purpose—for example, designing products, setting
up machines, operating machines, and distributing products.
* Activity Cost Pool :the overhead cost attributed to a
distinct type of activity For example: ordering materials or
setting up machines
* Cost Driver: any factor or activity that has a direct
cause-effect relationship with the resources consumed.
*
ABC allocates overhead costs in two stages
Stage 1:Overhead costs are allocated to activity cost pools.
Stage 2:The overhead costs allocated to the cost pools is
assigned to products using cost drivers.
4
Guidelines for refining costing system
1: Identify the Products that are the Chosen Cost Objects.
2: Identify the Direct Costs of the Products.
3: Select the Activities and Cost-Allocation Bases to Use for
Allocating Indirect Costs to the Products.
Steps for implementing Activity-Based
Costing ABC System
Step 1: Identify and Classify Activities and Allocate Overhead
to activity Cost Pool.
Step 2: Identify Cost Drivers.
Step 3: Compute activity-based Overhead Rates.
Step 4: Assign overhead cost to Products (cost objects).
5
Example 1 : On Implementing
Activity-Based Costing ABC System
(Step 1)
Overhead costs are assigned directly to the appropriate
activity cost pool.
* Identify Cost Drivers (Step 2)
Compute activity-based Overhead Rates per cost driver.
(Step 3)
6
Assign Overhead Cost to Products (Step 4)
Expected use of cost driver per
products
Expected used
of cost driver
per activity
Cost driver
Y N
1,000 500 1500 setups Number of
setups
35,000 15,000 50,000 Machine
hours
Machine hours
800 1,200 2000 inspections Number of
inspections
7
Assign Overhead Cost to Product N (Step 4)
=
Cost
assigned
×
activity-based
Overhead Rate
Expected use of
cost driver per
product N
Activity cost pools
$ 100,000 $ 200 500 Setting up Machine
150,000 $ 10 15,000 Machining
60,000 $ 50 1,200 Inspecting
$ 310,000 Total assigned costs
Assign Overhead Cost to Product Y (Step 4)
=
Cost
assigned
×
activity-based
Overhead Rate
Expected use of
cost driver per
product Y
Activity cost pools
$ 200,000 $ 200 1,000 Setting up Machine
350,000 $ 10 35,000 Machining
40,000 $ 50 800 Inspecting
8
Compute the overhead cost per unit for each product
(Unit produced 50,000 for N and 80,000 for Y )
Y N
590,000 310,000 Total assigned costs
80,000 50,000 Total units produced
7.375 6.2 Overhead cost per unit
Commenting on the comparative overhead cost per unit.
These data show that the total overhead assigned to 80,000
Y is nearly as great as the overhead assigned to 50,000 N .
However, the overhead cost per Y is $7.375 , It is only
$6.2 per N.
$ 590,000 Total assigned costs
9
Example 2 On ABC
Expected use of cost
driver per activity
Estimated
Overhead
Activity cost pools
1,000 orders $ 230,000 1- Customer orders
400 designs 252,000 2- Product design
20,000 size 380,000 3- Order size
250 Customers 367,500 4- Customer relation
Required
Calculate Activity - Based Overhead Rate
Solution
=
Activity-Based
Overhead Rate
÷
Expected use
of cost driver
per activity
activity
Estimated
Overhead
Activity cost pools
$ 230 per order 1,000 orders $ 230,000 1- Customer orders
630 per design 400 designs 252,000 2- Product design
19 per size 20,000 size 380,000 3- Order size
1,470 per Customer 250
Customers
367,500 4- Customer relation
10
Example 3 on implementing
Activity-Based Costing ABC System
The Lift Jack Company has seven activity cost pools and two
products. It expects to produce 200,000 units of its automobile
scissors jack and 80,000 units of its truck hydraulic jack. Having
identified its activity cost pools and the cost drivers for each
cost pool, Lift Jack Company accumulated the following data
relative to those activity cost pools and cost drivers.
11
Required
Using the previous data, do the following:
a. Prepare a schedule showing the computations of the
activity-based overhead rates per cost driver.
b. Prepare a schedule assigning each activity’s overhead
cost to the two products.
c. Compute the overhead cost per unit for each product.
d. Comment on the comparative overhead cost per unit.
Solution
a-Prepare a schedule showing the computations of the activity-
based overhead rates per cost driver.
14
c. Compute the overhead cost per unit for each product.
d. Comment on the comparative overhead cost per unit.
These data show that the overhead cost per unit assigned to
80,000 hydraulic jacks is nearly as great as the overhead cost per
unit assigned to 200,000 scissors jacks. However, the overhead
cost per hydraulic jack is $41. It is only $17.60 per scissors jack.